电网接入或延至2030年 微软放弃Nscale英国AI数据中心

19.10.2026

微软放弃 Nscale 在英国埃塞克斯郡Loughton的AI数据中心项目。当地电网运营商UK Power Networks告知Nscale,该站点最早要到2030年代初至中期才可能有足够电力容量,而项目原计划2027年初部署23,040块英伟达芯片,为Azure提供50MW算力。Nscale已清理场地并寻求其他供电方式,称其他微软合同不受影响。

微软放弃 Nscale 在英国埃塞克斯郡Loughton的AI数据中心项目。当地电网运营商UK Power Networks告知Nscale,该站点最早要到2030年代初至中期才可能有足够电力容量,而项目原计划2027年初部署23,040块英伟达芯片,为Azure提供50MW算力。Nscale已清理场地并寻求其他供电方式,称其他微软合同不受影响。

*Information provided in this article is for general information and reference only and does not constitute nor is intended to be construed as any advertisement, professional advice, offer, solicitation, or recommendation to deal in any product. No guarantee, representation, warranty or undertaking, express or implied, is made as to the fairness, accuracy, timeliness, completeness or correctness of any information, or the future returns, performance or outcome of any product. Bitdeer expressly excludes any and all liability (to the extent permitted by applicable law) in respect of the information provided in this article, and in no event shall Bitdeer be liable to any person for any losses incurred or damages suffered as a result of any reliance on any information in this article.