
Inside Bitdeer’s Crypto Mining Operation in Massillon, Ohio
2026.06.02
Bitdeer’s site at 1115 Industrial Ave. SW in Massillon, Ohio, is approximately half constructed, with eight of its 24 planned cryptomining buildings finished and the first "miners" having begun work in November 2025.
Media Coverage Summary: Inside Bitdeer’s Crypto Mining Operation in Massillon, Ohio
Originally published by the Canton Repository on June 2, 2026
Facility Scale & Operations
Bitdeer’s site at 1115 Industrial Ave. SW in Massillon, Ohio, is approximately half constructed, with eight of its 24 planned cryptomining buildings finished and the first "miners" having begun work in November 2025. All 24 buildings—measuring either 25-by-100 square feet or 25-by-200 square feet in two rows of 12—are expected to be complete by the end of summer. Operating similarly to a hyperscale data center, each building can hold more than 3,000 Bitdeer-manufactured Sealminer A2 Pro machines, totaling over 21,000 miners on site once finished.
Company Footprint & Production
Based in Singapore and publicly traded on the Nasdaq stock exchange, Bitdeer operates a vertically integrated portfolio that includes crypto mining facilities in Washington state, Texas, and Tennessee, with Massillon serving as its only current location in Ohio (alongside developing facilities in Niles and Clarington).
Cooling & Water Responsibility
The mining buildings feature remotely operated louvers, single-direction slanted roofs to shed snow and rain on the exhaust side, and narrow corridors separating air intake, central mining servers, and exhaust. Machine fans pull outside air through wall-length filters and a coated cardboard "water wall" designed to cool the machines like swamp coolers. While no water had been used since operations began in November, Bitdeer anticipates using 100 gallons a minute for a few hours per day in the summer, using city-supplied water that is collected in a trough and continually repurposed in site tanks with zero discharge.
Noise Mitigation & Power Infrastructure
To address community noise concerns raised prior to construction in 2024, Bitdeer built a 30- to 40-foot sound barrier near the closest residential area and pledged to keep noise at 60 decibels or less at the property line. The nearly $100 million facility—constructed with no property tax break—operates its own power substation opposite a FirstEnergy substation and uses up to 221 megawatts.
Local Workforce & Community Commitment
The Massillon facility currently employs about 40 workers and will expand to up to 70 employees—including operations technicians, electricians, and maintenance workers—when fully operational, offering starting wages of $22 an hour and an average salary of $82,000. Alongside donations to local city and community causes, Chief Communications Officer Ross Gan emphasized Bitdeer's long-term commitment to the area, stating, "We've made a commitment, also, that it's not just a site. We have to sink roots."

Read the full article on CantonRep.com: What's it like inside Bitdeer's crypto mining operation in Massillon?
*本文提供的资讯仅供一般参考,并不构成也不应被理解为任何产品的广告、专业意见、要约、招揽或建议,也不涉及任何产品的交易。对于任何资讯的公正性、准确性、及时性、完整性或正确性,以及任何产品的未来回报、表现或结果,比特小鹿(Bitdeer)不作出任何明示或暗示的保证、陈述、担保或承诺。在适用法律允许的范围内,比特小鹿(Bitdeer)明确排除与本文提供的资讯有关的任何和所有责任,并且在任何情况下,比特小鹿(Bitdeer)都不对任何人因依赖本文的任何资讯而产生的任何损失或遭受的损害负责。