Microsoft drops Nscale UK AI data center as grid power may not arrive until 2030s
2026.10.19
Microsoft has abandoned Nscale's AI data center project at Loughton in Essex, England. Local grid operator UK Power Networks told Nscale the site may not have sufficient power capacity until the early-to-mid 2030s, while the project had been planned to deploy 23,040 Nvidia chips by early 2027, providing 50MW of compute for Azure. Nscale has cleared the site and is seeking alternative power supply, and said its other Microsoft contracts are unaffected.
Microsoft has abandoned Nscale's AI data center project at Loughton in Essex, England. Local grid operator UK Power Networks told Nscale the site may not have sufficient power capacity until the early-to-mid 2030s, while the project had been planned to deploy 23,040 Nvidia chips by early 2027, providing 50MW of compute for Azure. Nscale has cleared the site and is seeking alternative power supply, and said its other Microsoft contracts are unaffected.
本文提供的資訊僅供一般參考,並不構成也不應被理解為任何產品的廣告、專業意見、要約、招攬或建議,也不涉及任何產品的交易。對於任何資訊的公正性、準確性、及時性、完整性或正確性,以及任何產品的未來回報、表現或結果,Bitdeer不作出任何明示或暗示的保證、陳述、擔保或承諾。在適用法律允許的範圍內,Bitdeer明確排除與本文提供的資訊有關的任何和所有責任,並且在任何情況下,Bitdeer都不對任何人因依賴本文的任何資訊而產生的任何損失或遭受的損害負責。